The Terminal 3 Modernization Design-Build program includes a major renovation to the Terminal 3 Passenger Processor Building, including consolidated security checkpoint, expanded check-in area, additional baggage processing capability, additional baggage carousels, expanded curbside services, and expanded concessions and retail. The South Concourse includes a new passenger concourse including expanded gates and expanded concessions and retail. The North Concourse includes a comprehensive renovation of the passenger and apron levels, renovation of gates, and an expansion at the mid-point as a ’node’ to accommodate additional amenities.
The Terminal 3 Modernization Project is a design-build construction contract awarded to a joint venture comprised of Hunt Construction, Austin Commercial, DWL Architects + Planners, Corgan Architects, and SmithGroup JJR Architects. The joint venture is commonly known as the HAJV.
Inspired Networks was contracted by the HAJV for Design and Delivery Management of the Special Systems outlined below. Inspired Networks lead the solution design, the planning/coordination, and the migration of eleven (11) airlines and the TSA to the consolidated Security Checkpoint.
Systems:
- Communication Systems
- LAN, WLAN, IPT, IPTV (DirecTV, CNN), DAS, Radio
- Security Systems
- CCTV, ACAMS
- Airport Operations Systems
- Airport Management System (AODB, RMS), EVIDS, Public Address System (PAS), Visual Paging, Hearing Loop, Interactive Directories, Queue Management, Digital Signage
- Passenger Processing Systems
- CUPPS, CUSS
- Parking Revenue and Management System
- Automatic Vehicle Identification (AVI)
- Airline Proprietary Systems
- TSA Proprietary Systems
Owner: City of Phoenix
Client: Hunt-Austin, A Joint Venture
Austin Commercial
Hunt Construction
DWL Architects + Planners
Corgan Architects
Smith Group JJR Architects
Construction Costs: $590 million
Completion Date: January 2020
Services:
- Survey and Documentation
- Stakeholder Interviews
- Due Diligence
- Planning and Estimates of Construction Costs
- Design Management
- Systems Design
- System Interface Design
- Construction Documents
- Construction Phase Services
- Client Interface
- Vendor Management
- Planning
- Procurement
- Delivery Management
- Project Management
- Staging
- Implementation
- Testing
- Commissioning
- Airline Relocations
- TSA Security Checkpoint Relocation